Brussels UIR Relief

Led by MUAC (2015 - 2017)

This MUAC initiative envisages the implementation of a 3rd layer in the Brussels sector group.

Sites involved

ACC/UAC : Brussels, Karlsruhe, Reims, Maastricht

Project description

The objective of this project is to achieve a better distribution of workload in the Brussels Sector Group (BSG), in function of the traffic composition at any given moment, by making available additional configurations based on:
- Olno-High as stand-alone sector: 02-04-2015 – implemented
- New DFL in the BSG West sectors (FL355): 04-02-2016 – implemented
- Third Layer in the BSG East sectors: 02-03-2017 – implemented

Implementation Steps

Period
StartEndLed by
Implementation04/201512/2017MUAC