SYSAT

Led by DSNA (2017 - 2023)

Sites involved

TMA : LFPG, LFPO, LFMN, Non PCP DSNA

Project description

The SYSAT program objective is to replace, modernize, and improve efficiency and homogeneity at national level of the ATM tower and approach systems which are under DSNA’s responsibility.
It involves all continental DSNA APPs/TWRs (about 70 big, medium and small sites), excluding oversea facilities.

Implementation Steps

Period
StartEndLed by
LFPG TWRs + APP10/201710/2019DSNA
LFPO TWR + APP10/201906/2020DSNA
LFPB TWR03/202006/2020DSNA
Other APP/TWRs06/201912/2022DSNA