Continuous Decent Operations Procedures

Led by DFS (2017 - 2024)

This DFS initiative provides the Approach Procedures allowing Continuous Descent. It involves Langen, Munich, Karlsruhe, Bremen and all 10 DFS Towers

Sites involved

TMA : EDDF, EDDM, EDDL, EDDT, Non PCP DFS

Project description

More in particular; it is about the implementation of 10 CDO procedures at major German aerodromes until 2014. Only the envisaged implementation at the new Berlin Airport (BER) was postponed due to the delay of the opening of the airport. During 2016 there will hence be the implementation of a CDO procedure for Berlin-Tegel (TXL)
The implementation at Tegel was completed 06/2016.

Implementation Steps

Period
StartEndLed by
Implementation01/201712/2024DFS