High-Profile Transition Operation (HTO)

Led by DFS (2014 - 2017)

CDO with pre-programmed vertical guidance (e.g. STARs) into EDDF from cruising level.

Sites involved

ACC/UAC : Karlsruhe, Langen, Munich
TMA : EDDF

Project description

High-Profile Transition Operation (HTO) : establish Continuous Descent Operations (CDO) with pre-programmed vertical guidance (e.g. STARs) into EDDF from cruising level. It involves the ACCs of Langen and Munich and UAC Karlsruhe.

Implementation Steps

Period
StartEndLed by
Development01/201409/2016DFS
Implementation06/201612/2016DFS
Monitoring Period 110/201603/2017DFS
Re-Design ASPAT STAR10/201706/2018DFS
Monitoring Period 210/201712/2018DFS